The Club Dig

Home Our Headquarters How To Find Us Trips and Events Meet The Team The Club Dig Club History Caving Web Links Cave Development For Newcomers


The Brickworks Dig

Ogof Gweath Brics

Map Reference: SN 8552 1526
Altitude: 335m

This project was started in 1986.  The Club has been involved in various dig projects throughout its history but this is the one we have always returned to.
 

brickworks dig.jpg (45323 bytes) wpe7.jpg (25925 bytes) pulling.jpg (14173 bytes)
The entrance The surface party hard at work Pulling out the truck

No "rabbit-holing" in this dig.  All of the spoil, literally tons of it have been brought out to the surface using a railway system.

tipping.jpg (12481 bytes) wpe1B.jpg (17449 bytes)

Tipping the spoil

Looking back up the entrance slope.  The side passage is on the right.

Dig Activity in 2000

We visited Ogof Gweath Brics on Saturday 5th February 2000.  The previous week had been very wet and there was too much water at the dig face for us to be able to bale it out in a reasonable time so instead we dug out another 8 feet or so of the Side Passage.  The un-surveyed passage is trending downwards and will probably connect to the dig face.

Our next visit was on Sunday 12th March 2000 following another fairly damp week.  The water was a little lower than last time but still too high for us to be able to dig in Lower Main Passage so we completed digging out the Side Passage - it did connect and Keith was the first Club member to complete the "round trip".

Jim, Mick, Brendan and Keith visited the dig over the weekend of 27th and 28th May.  The dig truck had been vandalised, had lost a tire and needed re-welding. Over an inch of rain had fallen on Friday night but the water level was still below the level of the railway track - just.
We used the propane pump which shifted over a thousand gallons of water in a little over ten minutes.  However by the time the fumes had cleared over half of the water had flowed back in.  Nevertheless we shifted 75 buckets of infill over the weekend.  There is now a large void at the dig face with loads of "hanging death" in the ceiling.  Immediately in front of us there appears to be a solid cave wall.
Keith took some video of the proceedings.

wpeC.jpg (16380 bytes) wpeF.jpg (20539 bytes) wpe11.jpg (20691 bytes) wpe13.jpg (29018 bytes)
Keith and John in Lower Main Passage on the day it was discovered. Jim in the same place on 5th February 2000 - slightly damper! Jim in the side passage on 5th Feb - slightly muddy! Jim emerging from the dig chocolate factory.

The last visit for digging in 2000 was on the weekend of 18th-20th August. We pumped out a large volume of water late on the Friday night. Unfortunately when we visited to dig the following morning we found that some "no brain" (Keith) had left the propane cylinder turned on over night and the cave was full of potentially explosive gas!  Nevertheless we managed to dig all of Saturday and cleared a four to five foot section of floor. In the floor is a foot wide slot. We knocked a scaffold bar four feet into the slot with very little resistance. We also removed a lot of spoil from the dig face but cannot undermine the "hanging death" any further unless we undertake some serious scaffolding.
Due to lack of volunteers we were unable to dig on the Sunday and so went caving instead.

Dig Activity in 2001

We were not able to visit the dig in 2001 due to the Foot and Mouth situation.

Dig Activity in 2002

Brendan visited the dig on Saturday 9th March and found that part of the roof of the aven had collapsed in from the surface.  So the dig now has a "through trip" to add to the "round trip".
John, Graham, Roger, Keith and Brendan spent Saturday 6th April capping and making safe the recent surface collapse above the aven.  When Brendan had first spotted the collapse 4 weeks before the hole had been about the diameter of a dust bin.  When we arrived the hole had grown to be about 4 to 5 feet across.
We also spent an hour of so digging in the base of the quarry on the opposite side of the tram road but to no avail and finally returned to the Brickworks to pull out about 25 buckets of the recent infill.

wpe3.jpg (131203 bytes)
The old and the "temporary" new entrance.

wpe5.jpg (120474 bytes)
John placing railway sleepers in place above the hole.

wpe7.jpg (136169 bytes)
Finishing off by sloping the sides of the depression.

The dig was next dug on the Sunday 18th August by GS, JS, MB, BM, MC & EP. We have started piling the fill which came in from the surface into sand bags and have built a lovely retaining wall with it up in the chamber. Looks like it should work quite well. Spoil removed down to track level as far as the turn left.

The dig has collapsed to surface again - late October.  The new hole is to the right of the original one.

Dig Activity in 2003

25th/26th January  John, Graham, Brendan and Keith spent this weekend working at the Brickworks, building terraced walls from the scaffold tower.  Another weekend's work should see the dig capped once again.

15th/16th February  John, Graham, Brendan, Adrian, Mick, Jim (yes Jim) and Keith spent the weekend on 15th/16th February working at the Brickworks.  The hole to surface has now been capped once again.  There is still a lot of infill to remove from below the scaffold tower as the original route into the cave is now completely blocked.
The dig face looks very interesting with the possibility of two rifts to be dug out - one straight on and one to the right.


The hole taken from SWCC HQ


Brendan Marris in the hole

22nd/23rd March  The digging team consisted off: Pete Anstey (Sat. only), Mick Bowdler (Sun. only), Keith Edwards, Andy Grimes (Sat. only), Brendan Marris, Graham Smith, John Smith and Adrian Stanley.  During the weekend most of the infill was removed from below the scaffold frame.  Truck repairs were necessary on the Saturday evening.

8th June  A day digging on the Sunday by Keith Edwards, Brendan Marris, John Smith and Adrian Stanley, after a trip in OFD 2 on the Saturday.  The infill below the scaffold frame has now been cleared to track level and below.  The original route into the cave is now passable once again.

13th July  The team this time consisted of Roger Bryan, Keith Edwards, Brendan Marris, Graham Smith, John Smith and Adrian Stanley.  All of the infill from the collapse has now been cleared and the floor re-exposed in Lower Main Passage below the railway track.  We are ready now for the big push forward.

Keith demonstrating the re-exposed floor in the side passage

John clearing the side passage

John taking a break from digging and enjoying a well-earned cuppa

Sunday 14th September  A very tired (from the previous day's caving and walking) digging team cleared a lot of the infill from the pile by the dig face.
BMa & GSm took the first underground shift and KEd & ASt the second one.
The rift straight ahead shows no signs of opening out lower down.  The right-hand rift still needs further investigation.

The Dig Team: MBo, KEd, BMa, GSm, JSm & ASt

Dig Activity in 2004

14th/15th August  A very successful digging weekend. In spite of the recent inclement weather there was only about 2' 6" of water at the lowest point. Saturday was spent bailing then digging with 45 buckets of infill removed to the surface. Sunday was spent mainly on scaffolding the around a large boulder and creating a scaffold roof for the protection of the digger. At the end of the day a further 15 buckets where removed. We have proved that the way on is to the right at the dig face with solid walls and roof! During the weekend we added another 6 feet to the length of the cave. We aim to return soon to complete the scaffolding and add more passage to the survey.

The Dig Team: JDu (Sun only), KEd, BMa, GSm, JSm & ASt


Adrian examining the scaffolding.
The way-on is behind the shored-up boulder on the right

25th/26th September  One of the most successful dig weekends ever.  Much of the weekend was spent scaffolding and stabilising the area before the final right turn, but we still managed to remove 105 buckets of in-fill and add another six feet to the length of the system.

The Dig Team MBo, KEd, BMa, JSm & ASt


Dig Activity in 2005

Weekend 28th/30th January  Keith, Brendan, Graham, John and Keith travelled down on the Friday evening.  The water level at the lowest point was just a little over welly height so it was decided to pump it out.  Once the pump had been started this took only about 5 minutes.
Adrian joined the team on Saturday and with Brendan acting as Duty Officer at the club, five of us dug out another 5 feet of passage, removing 105 buckets of infill.
On Sunday the team was strengthened by the addition of Pete, Mick Bowdler, Mike Cavanagh, Jim and Mike Noble.  Approximately 120 buckets of infill was removed.
The passage discovered last August (Extension Passage) is now a little over 20 feet long with solid roof and walls.  It is trending downwards at on angle of approximately 5 degrees and has been dug out to a depth of about 3 feet 6 inches.

The dig team

Pete removing a boulder
 

The new passage - Pete in the foreground and Jim behind

Mike Noble at the dig face

The Dig Team: PAn (Sun only), MBo (Sun only), MCa (Sun only), JDu (Sun only), KEd, BMa, MNo (Sun only), GSm, JSm, ASt & CWe


Weekend 7th/8th May  Another very successful digging weekend.  On Saturday morning we constructed a single-bucket railway over the pool and in the afternoon we removed 75 buckets of spoil.
On the Sunday we removed another 112 buckets of infill.
We appear to have discovered a cross-rift with the passage we have been following, continuing ahead.  Another weekend should confirm this.  During the weekend we added 6 feet to the length of the cave.

The Dig Team: MCa (Sun only), KEd, BMa, MNo, GSm, JSm & ASt


Keith Edwards in the newly discovered cross-rift.


Weekend 11th/12th June  Yet another highly successful weekend's digging by a very small, but highly dedicated team.
After a sunny week we all expected the dig to be dry, but the Extension Passage had a significant amount of water at its lowest point. We managed to bail this back into the main pool and then went to examine the dig face.  There was foam high in the roof of the cross rift indicating that the Extension Passage had recently flooded to the roof.  The water had washed some of the infill out of the passage straight ahead and had exposed a large pointed boulder hanging down from the roof.
Brendan used his electronic draught detecting meter and found a small be significant draught to the left hand side of this boulder.
During the Saturday Adrian continued to dig ahead and managed to get underneath and past the hanging boulder - 60 buckets of infill were removed on the day.  On the far side of the boulder the passage roof effectively disappeared with only sand above the digger.
On the Sunday Keith investigated the roof behind the hanging boulder with the aid of a 4' length of angle iron.  After about half a dozen prods the bar went through to reveal black space.  After about half an hour the hole in the roof was large enough to climb up into.  We are in a narrow rift about 7' 6" high (from the existing floor) with about 3" of air space in both directions.  The passage back to the cross-rift has been dug out to body-size and will connect to the top of this rift.  A small air space can be seen to both left and right along the cross-rift.  The left hand passage (looking into the cave) seems to be an inlet.
Ahead the passage continues with air space at roof level.  Approximately another 5' of this passage has been dug out.  It is a narrow rift - about a foot or so wide and so although air space exists at roof level the passage will have to be dug out to the existing floor level where hopefully it will continue to be wide enough to get through.  Another 36 buckets of infill were removed to surface on the Sunday.


The newly discovered passage looking up-dip, back towards the entrance

 


The newly discovered passage looking down-dip, the way on

The Dig Team: MCa (Sun only), KEd, BMa, MNo & ASt


Weekend 9th/10th July  A large dig team and probably a record for the amount of infill removed - 140 buckets on the Saturday and 120 buckets on the Sunday, but nevertheless a little disappointing.
There was a lot of water in the extension passage and so the first couple of hours on the Saturday was taken up in baling water from here to the main pool and from the main pool to the surface.
When digging commenced it became apparent almost immediately that the rift ahead was joined in the middle.  Above (where the air space is) the passage is too small to follow, below we could see an arched roof.  Unfortunately by the close of play on Saturday is was impossible to remove any more infill ahead as most of the way on was below water.
On Sunday John and Adrian lowered the floor by the dig face and ramped it back along the passage.  Now the water drains to the bottom of the passage and so should be easier to bale out next time.  Before we can go digging again we will need to source a pump.
During the weekend approximately 2 feet was added to the length of the system and about 6 feet to the depth.

The Dig Team: PAn, MBa, DBo (Sun only), KEd, BMa, MNo, JSm, ASt & CWe


Dudley Caving Club   Dudley Caving Club   Dudley Caving Club   Dudley Caving Club   Dudley Caving ClubTop

TO CONTACT US:

PHONE: Emma Porter or Mike Clayton on 0121 565 5401
or E-MAIL: I've removed the mail to: link to reduce the amount of junk mail I get.  Sorry but now you will need to type my email address into your email client.

This Web site was designed and created by Keith Edwards.
Copyright Dudley Caving Club 1997 - 2005